1、电蒸汽锅炉http://www.jnshengxin.cn/及其辅机、水处理设备等的安装应符合设备制造厂的技术要求,设备基础必须待设备到货并与设计图纸核对无误后,方可施工。
Installation of electric steam boilers and auxiliary equipment, water treatment equipment, etc. shall comply with the technical requirements of equipment manufacturers, equipment foundation must be after the arrival of equipment and design drawings and check and correct, before construction.

2、电蒸汽锅炉管道最高点放气、最低点放水。
Electric steam boiler tubes deflate the highest point, the lowest point of water.

3、电蒸汽锅炉管道安装后的试压验收,按《工业金属管道工程施工及验收规范》进行。
Pressure test after acceptance electric steam boiler pipe installation, according to the "industrial metal pipeline construction and acceptance of" conduct.

4、电蒸汽锅炉http://www.jnshengxin.cn/锅炉房内所有用电设备及蓄热装置等都应可靠接地。
Should be grounded electric steam boilers and boiler room all electrical equipment thermal storage devices.