1、安全阀是最后一道安全保障,应定期进行灵活性检验,每个月最少二次快速拉动安全阀的拉杆以检查它的起跳和回座的灵活性,若安全阀不能起跳或者不灵活,请立即更换。安全阀每年应定期到当地的质监局进行校验。
Safety valve is the last security, flexibility should be regular inspection at least twice a month fast relief valve lever to pull it off and check the flexibility of the back seat, if the valve can not take off or not flexible, immediately replacement. Safety valve should be regularly every year to the local quality supervision bureau for verification.
2、锅炉在使用时应配备软化水处理器,在保证水质硬度较低时才能保证电热管的使用寿命,因水垢严重导致电热管损坏不在保修范围内。
Boilers should be used with softened water processor, at lower water hardness assurance to ensure the life of the heating pipes, heating pipes because of scale resulting in serious damage not covered under warranty.
3、第一次使用本产品时,设备运行前先用一字螺丝刀将锅炉给水泵的排气螺丝拧松,将里面的空气排尽直至冒水,然后再将螺丝拧紧。
The first time you use this product, the first device to run the boiler first with a flathead screwdriver to loosen the vent screw pump, the air inside to take up water drained, and then tighten the screw.
4、每天第一次使用前须将蒸汽阀门打开,后打开排污阀至炉内的水及污物完全排尽。
A day before the first use of steam required to open the valve, open the drain valve to the furnace is completely drained of water and dirt.
5、检查水箱以保证水箱内清洁、没有杂物,防止垃圾进入管道损坏水泵或卡死止回阀。
Check the water tank to ensure the tank clean, no debris, garbage into the pipe to prevent damage to the pump or stuck valve.
6、关闭排污阀,蒸汽阀门仍然开启,启动蒸汽发生器的电源开关,此时发出缺水报警,水泵运转对蒸汽发生器补水,直至炉内水位高于低水位时报警声停止并同时接触器吸合启动加热,当水位达到高水位时水泵停止补水。
Close the drain valve, steam valve is still open, start steam generator power switch, this time to issue water alarm, pump operation of the steam generator water until the water level is higher than the alarm sound when the furnace is stopped while low water contactor close start heating, when the water level reaches the high water pump stops water.
7、蒸汽发生器的管路安装时必须考虑防止被加热物倒罐及管路冷凝水的排放等因素。
The steam generator must be considered when mounting the pipe elements to be heated to prevent the pouring conduit and the discharge of condensate and the like.
8、当您检修锅炉或者更换电器部分配件时,请切断电源以免带电工作造成危险。